MORE Power Targets 2026 Energization of Philippine Substation as Vietnamese Transformer Supply Supports Grid Expansion

MORE Electric and Power Corporation is accelerating construction of its General Hughes substation in Iloilo City, Philippines, with energization targeted before the end of 2026. The project includes a 30/36 MVA power transformer imported from Vietnam on October 8, a 69 kV connection extending 4.3 circuit kilometers, on-load tap changing technology, and thermal monitoring systems.

Author: Akshay Reddy

Editorial Review: Akshay Reddy

Published on:

What Happened

On November 9, 2026, Philippine newspapers reported that MORE Electric and Power Corporation (MORE Power) is accelerating construction of its General Hughes substation in Iloilo City, with energization targeted before the end of 2026. The utility plans a 30/36 MVA power transformer and a 69 kV connection extending 4.3 circuit kilometers. The transformer was imported from Vietnam on October 8, making the shipment a previously completed procurement milestone rather than a new November 9 order.

The station will incorporate an on-load tap changer for voltage regulation and thermal cameras for equipment monitoring. MORE Power expects its combined substation capacity to reach 288.5 MVA after completion. Neither a final equipment contract value nor individual component prices were disclosed in the new reporting.

  Request Demo: https://www.datamintelligence.com/electroiq#demo 

Why It Happened

MORE Power says the project is designed to address persistent low-voltage conditions in Iloilo City's central business and administrative district. Placing additional transformation capacity near these loads can reduce voltage drops and provide flexibility as demand grows.

The intended service area includes City Proper customers, city-government facilities and public markets. The utility also aims to maintain operational loading around 60%-70%, according to its reported planning guidance; this is an operating objective, not a verified post-commissioning achievement.

The project continues a wider program of new substations and refurbishment of inherited network assets, rather than representing a sudden change in regional electricity demand.

Market Impact and Equipment Lead Times

The development demonstrates cross-border sourcing in Southeast Asia's electrical-equipment supply chain: a transformer manufactured abroad has been delivered for a Philippine distribution-grid project. Its installation can create associated demand for medium- and high-voltage breakers, cable terminations, protection relays, control panels, conductors, insulation and substation-monitoring equipment. However, these potential requirements are not all newly awarded contracts.

MORE Power's original 2025 procurement documents specify two 30/36 MVA transformers for separate Megaworld and General Hughes sites. The rating describes alternative operating capacities for each unit; it is not evidence that General Hughes is receiving two transformers. The documents also specified delivery within 240 calendar days after a notice to proceed. That was a tender requirement, not an industrywide lead-time benchmark or confirmation of actual delivery performance.

Similarly, the reported 4.3 circuit-kilometer line extension does not translate directly into 4.3 kilometers of purchased conductor. Phase configuration, circuit arrangement, conductor size and installation design determine material quantities.

Successful energization will require construction completion, integration of protection and control systems, inspection and testing. Transformer delivery on October 8 does not establish that those remaining steps have been finished. Equipment manufacturers and contractors should treat the end-2026 energization date as a target, not a guaranteed milestone.

  Request Demo: https://www.datamintelligence.com/electroiq#demo 

DMI Opinion

DataM Intelligence considers the project a useful example of how urban voltage-reliability problems can translate into targeted demand for transformers, tap changers and associated network components. The international sourcing element matters, but one shipment does not prove a global transformer shortage or a sustained increase in equipment prices.

Suppliers should track installation progress, equipment qualifications and follow-on tenders. Utilities should distinguish delivered hardware from commissioned capacity. The project's measurable industry impact will depend on successful energization and demonstrated service improvements.

Found it interesting?

Email: [email protected]
US: +1 877 441 4866

We have 10,000+ research reports serving across 100+ countries